Telecommunications
Timeline
Key Dates
- Phase 1 March 7 – 8
- Phase 2a March 17 – 18
- Phase 2b March 26 – 29
- Phase 2c March 31 – April 4
- Phase 2d April 7 – 8
- Phase 3 April 18 – 20
- Phase 4 May 2 – 4
- Phase 5 May 16 – 18
Campus Deployment
The following buildings are now on the new telephone system:
- Alumni House
- Parrish Football Center
- Hanner
- Iron Works
- Wiggins Baseball Bldg & Stadium
- Hollis
- Family & Consumer Science
- Nursing-Chemistry
- Interior Design Bldg & Cottages
- Child Development Center
- Business Administration Bldg (COBA)
- College of Information Technology (IT Bldg)
- Carroll
- Newton
- Fine Arts
- Center for Arts and Theater
- Ceramic Sculpture and Scene Shop
- Forest Drive Classroom Bldg/
-
- Hendricks Hall
- Math/Physics Bldg
- Henderson Library
- Herty
- Biology
- IAP
- Carruth
- School of Technology Bldg
- College of Education
Building Cutover Schedule 4-24-08b.xls
Page was last modified on Friday April 25, 2008 at 2:30pm