Replacement of Selected Transformers

 
Quick Facts
Architect:
-
Contractor:
Clay Electric
GSU Project Manager:
mr. Billy Harris
GSU Construction Manager:
Mr. David Campbell
Construction Dates:
Start Date: July 2009 Completion Date: December 2009
Description

Replacement of the following transformers:
Russell Union (T-13)       Nessmith Lane (ST-45)
Hanner (ST-43)              M.P. Administration Bldg.(ST-23)
Deal Hall (ST-22)

Near Term Expected Work
The contractor has his work force ready for the transformer change outs in November.

Monthly Progress - September 2009
A generator will be provided for the Marvin Pittman Administration building to provide power for the servers.

Monthly Progress - August 2009
A coordination walk thru for all transformers has been conducted with the contractor and physical plant personnel. The contractor has his workforce ready for the transformer change outs in November.