The new Alumni/Welcome Center facility will be an accessible, friendly, and warm place for first time visitors and returning alumni. The facility of approximately 12,000 GSF will house the Alumni Center and Welcome Center with related functions.
Near Term Expected Work
Complete store fronts and windows. Start wood ceiling and ceramic tile at Alumni Hall. Limestone to be 90% complete. All brick will be completed at front entrance of building. Finish wall painting and complete ceiling tile to 90%. Start carpet on west wing of building and pavers at back entrance of Alumni Hall.
Monthly Progress - March 2009
Windows and store fronts are 98% complete. Started limestone on site at front and back entrances. Limestone tile on fire place at Alumni Hall is 95% complete. All ceiling grid in building has been installed. Started final grading on east side of site.
Monthly Progress - March 2009
Lightning protection has been installed. Windows are 95% installed. Ceiling grids and painting started in the west wing. Sheet rock walls in the Alumni Hall installed. Data cable/cable lines are being installed.
Monthly Progress - February 2009
All framing is complete and 95% of sheetrock is complete. Metal roofing and capping has been completed. Store front windows have been delivered and installation started. 95% of all electrical, plumbing, HVAC, fire piping has been installed. Outside grading has started on some parts of the building with concrete patios installed. Ceramic tile has started in both men and women’s restrooms.
Monthly Progress - January 2009
Detail stud framing has started on the inside of building. Brick work is complete on extra of building. Metal roofing is app 90% complete. Rough in plumbing and electrical is 90% complete. Mechanical yard complete with power to the building. HVAC insulation started and rough in fire sprinkler piping is being installed.
Monthly Progress - December 2008
Stud framing complete with sheetrock started. Brick work 95% complete. Roofing membrane installed. Rough in electrical and plumbing in progress. HVAC rough in started. Building is dried in at this point. Insulation started in roof area.
Monthly Progress - November 2008
Steel work complete. Metal studs 90% complete. Block work complete. Roof trusses complete. Rough in electrical and plumbing in progress. Ply roofing started.
Monthly Progress - October 2008
Footers are complete. Building concert slab complete. Steel erection 90% complete. Metal studs have been started on west wing of building. Rough in of race wire conduit, and plumbing piping is complete.
Monthly Progress - September 2008
Digging and pouring footers. Block masonry work. Rough in plumbing. Chilled water piping installed and tested.
Monthly Progress - August 2008
Ground breaking began. Started on layout. Began digging and pouring concrete footers
Monthly Progress - June 2008
Contract awarded to Y-Delta. Contracts have been signed by the BOR and have been delivered to the contractor.
Monthly Progress - May 2008
Sent documents to LDD. Architects to complete set by the end of April. Project will go out for bid in May 2008.
Monthly Progress - April 2008
Sent documents to LDD. Architects to complete set by the end of April. Project will go out for bid in May 2008.
Monthly Progress - March 2008
Waiting on final documents from architect. Reviewed final drawings.
Monthly Progress - February 2008
Approved by Board of Regents in February 2008.
Monthly Progress - January 2008
Approved by Board of Regents in February 2008.
Monthly Progress - December 2007
Program is finalized. Construction documents are 90% complete.
|